The topic of the new series of paintings is a presentation of A SPECIFIC PLACE and AN EVENT within that place. The place can be real or imagined yet what makes that place become specific is the quality of its light and what makes up its landscape. What depicts the event or narrative occuring within that place is the presence of a person and/or a prop/s. Currently my locations for this body of work are suburban Sydney, Australia; Milan, Tuscany, Palermo, Italy and London United Kingdom. These will provide ingredients for the new scenes and places that I aim to re-present.



Wednesday, November 4, 2009

October Work Progress

The first set-back being the discovery of an archaic insulation system consisting of soot and soil upon which rested the floor-boards.
This requires replacing with an adequate concrete slab minimizing beam deflection and optimizing the floor stability




soot and dirt being dug out from in between the floor joists


all the old floor boards ready to go


The next set of photos are from the third on-site meeting at the end of October. The space in between joists has been filled with cement, hooks have been added to the joists to fix the wire mesh onto them, and secure the slab once it is cast. This should allow for a very stable floor with even loading of the floor beams.


cement & hooks

wire mesh welded to the hooks


rods will be cast in the slab and fixed with epoxy resin to the perimetral walls


The second set-back descovered during the demolition works, being that of the ceiling being entirely plasterboard rather than plastered brick-work. This requires removal in order to fix new soffit panels and insulation to the structural ceiling slab.




removal of the wood panelling from windows and doors to be refurbished

Doors waiting to be taken off-site for sanding and painting


examining the blinds enclosure panel to decide how it should be replaced


The last discovery to be made on site has been that of a narrow clogged up soil-vent pipe. The previous occupiers (dentists) having illegally poured alginate down the sinks causing the further reduction to the
diameter of the s.v.p which will need replacement. Possibly requiring access from the floor below to proceed with the works. Lets see what else remains to be discovered.




less than 90mm to start with, going down to 75mm further down the pipe